[Imc-tech] Problem with calendar
Daniel S. Lewart
d-lewart at uiuc.edu
Sun Jun 3 03:44:58 CDT 2001
Ellen,
> The software running the calendar is not matching the right day to date in
> the month beginning with June. When you first switch over to June the days
> are off by two... that is June actually starts on a Friday but it shows
> that it starts on Sunday. However if you click on a day to view that days
> events and then click on view Month it rights itself. I imagine that the
> problem with June will be fixed in about 20 minutes when it is officially
> June because it automatically goes to the detail view of the day. But I
> would also guess there would be a problem with July forward.
Good eye!
> This message may not make sense unless you actually look at the calendar
> and try looking ahead. I have no idea how to fix this.
Here's what happened. The date was May 31. The Microsoft quality
software figured "next month" was Jun 31 [sic]. This got converted and
reverted to Jul 1. Thus, it showed the month after May as Jul.
It was a one-line fix.
> PS I have some other suggestions about the calendar that I will explain
> detail in another email.. probably tomorrow.
Cool. FYI, I'll miss the Wed meeting.
Thanks!
Dan