Back-back room to do list version 1.0:
1. [DONE] Move equipment out of back-back room.
2. [ ] Set up PA system.
3. [ ] Finish & connect electrical wiring.
4. [ ] Finish insulation installation.
5. [ ] Sweep/Vacuum floor.
6. [ ] Mop floor.
7. [ ] Paint wall with hanging doors.
8. [ ] Debug sound system.
9. [ ] Get space heaters & fuel.
10. [ ] Move mantle-style furniture to 2nd floor.
11. [ ] Set up snack-prep area.
12. [ ] After floor is clean, move furniture into back-back room.
13. [ ] Dust rafters.
********************